Stage statusODP StageODP NameStage start date Stage end dateMeetings / MinutesRelevant documents
(tick)1Project initiation1 June 201430 June 2014Meetings & minutesProject proposal
(tick)2Stakeholder mobilization1 July 201431 October 2014Meetings & minutes 
(tick)3Developing initial draft1 October 201421 October 2016Meetings & MinutesRevised draft Recommendation on Zero Tolerance to Corruption in PPP Procurement (March, 2016)
(warning)4Public review31 October 201631 December 2016Meetings & Minutes

Draft for Public Review version 1.0 (October, 2016)


Template for comments and observations


Comments Log

 5Endorsement    
 6Approval    
  7Maintenance    

...